At 10:00 a.m. on September 26 Nigerian time, the generator stator of 2# unit of Zungeru Hydropower Station - the largest hydropower station in Nigeria, jointly constructed by CNEEC and SINOHYDRO, was successfully hoisted into the pit, completing another important milestone of the project. After the lifting of 1# stator on April 18, the successful lifting of 2# stator marks the smooth progress in the overall installation work of 2# unit, and a steady step towards the realization of connecting 4 units to the grid next year.
ADD : CNEEC BLDG., 9, SOUTH SHOUTI RD., HAIDIAN DISTRICT, BEIJING 100048 P.R.CHINA
TEL : (8610)68798899
FAX : (8610)68798000
E-MAIL : cneec@cneec.com.cn
Beijing ICP No. 17028836 Copyright©China National Electric Engineering Co., Ltd. , All Rights Reserved